METHUEN- RESURFACING & RELATED WORK ON ROUTE 213 INCLUDING DECK REPLACEMENT, M-17-024 & M-17-025, ROUTE 213 (EB & WB) OVER SPICKET RIVER & SUBSTRUCTURE REPAIRS, M-17-033, I-495 (NB & SB) OVER ROUTE 213
The project will resurface Route 213 in Methuen from milepoint 0.0 to 3.6 along with replacing the deck of M-17-024 and M-17-025, eastbound and westbound, over the Spicket River and performing substructure repairs to M-17-033 on I-495, northbound and southbound, over Route 213.
Location:
  • Town of Methuen
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Michael Pavao
    Construction Bid Price: $9,719,194.00
    District: District 4

    Contracts (1) Progress
    # 96795 -- Construction Contract
    Resurfacing and Related Work (Including 4 Bridge Decks) along the Route 213 Loop Connector. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/06/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2013
    Project Initiation Form PIF Entered 05/14/2013
    Project Initiation Form PRC Submitted 05/14/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 08/06/2016
    Project Management
    100% Design 100% Package Received 02/19/2016
    25% Design 25% Package Received 08/03/2015
    25% Design 25% Package Comments to DE 11/25/2015
    75% Design 75% Package Received 08/03/2015
    75% Design 75% Package Comments to DE 11/25/2015
    Final Design PS&E Received 02/19/2016
    Final Design PS&E Received 06/17/2016
    Final Design PS&E to FAPRO 07/25/2016