Project Description:
SOUTHBOROUGH- RESURFACING & RELATED WORK ON ROUTE 9, FROM THE FRAMINGHAM T.L TO WHITE BAGLEY ROAD
The proposed project involves resurfacing and related work on Route 9 in Southbrough. The project begins just west of White Bagley/Breakneck Hill Road (mm 111.4±) and ends at the Framingham/Southbrough town line (mm113.0±) for a distance of 1.6 miles. The proposed improvements also include minor improvements to existing traffic signals, reconstruction of existing sidewalk and may include construction of additional sidewalk if feasible. Related work includes upgrades to guardrail and signs.
Location:
  • Town of Southborough
  • Construction Begins: Spring 2018
    Resident Engineer: Linda Terry
    Construction Bid Price: $3,737,531.65
    District: District 3

    Contracts (4) Progress
    # 102206 -- Construction Contract
    Resurfacing and Related Work (Including Signals) along a Section of Route 9 (Turnpike Road) Completed
    # 56818 -- Design -- Services
    Work will consist of providing statewide photogrammetric services on an as need, assignment basis over a period of 60 months. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/21/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/03/2013
    Project Initiation Form PIF Entered 04/03/2013
    Project Initiation Form PRC Submitted 04/03/2013
    Project Review Committee PRC Approved 04/04/2013
    Project Status Advertised 09/09/2017
    Project Management
    100% Design 100% Package Received 12/29/2015
    100% Design 100% Package Comments to DE 02/19/2016
    25% Design 25% Package Received 10/15/2014
    25% Design 25% Package Comments to DE 11/10/2014
    25% Design 25% Package Comments to DE 01/07/2015
    25% Design 25% Package Comments to DE 01/09/2015
    25% Design 25% Package Comments to DE 03/11/2015
    25% Design 25% Package Comments to DE 06/29/2015
    25% Design Design Public Hearing 10/27/2015
    75% Design 75% Package Received 12/29/2015
    75% Design 75% Package Comments to DE 02/19/2016
    Final Design PS&E Received 06/09/2016
    Final Design PS&E to Peer Reviewer 06/09/2016
    Final Design Peer Review Comments to DE 07/15/2016
    Final Design PS&E Received - Resub 1 04/12/2017