Project Description:
BOSTON- MILTON- SYSTEMATIC MAINTENANCE & STRUCTURAL REPAIRS TO 7 BRIDGES ALONG THE I-93/ US 1/ST 3
Bridge Cleaning, Deck Joint Repairs, Reinforced Concrete Excavation, Epoxy Coating of Substructure Surfaces, Concrete Repairs, and Steel Cleaning and Painting of Two Bridges.
Location:
  • City of Boston
  • Town of Milton
  • Resident Engineer: Carmine LaVita
    Construction Contract Value: $2,629,996.50
    Construction Bid Price: $1,881,815.00
    Initial Construction Estimate: $1,507,000.00
    District: District 6

    Contracts (1) Progress
    # 85330 -- Construction Contract
    Cleaning, Painting and Structural Repairs to 7 Bridges along Interstate 93/US1/ST3 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/26/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/11/2013
    Project Initiation Form PIF Entered 04/11/2013
    Project Initiation Form PRC Submitted 04/11/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 10/11/2014
    Project Management
    100% Design 100% Package Received 05/02/2014
    Final Design PS&E Received 09/30/2014
    Final Design PS&E to FAPRO 10/01/2014