| Project Description: |
BOSTON- MILTON- SYSTEMATIC MAINTENANCE & STRUCTURAL REPAIRS TO 7 BRIDGES ALONG THE I-93/ US 1/ST 3
Bridge Cleaning, Deck Joint Repairs, Reinforced Concrete Excavation, Epoxy Coating of Substructure Surfaces, Concrete Repairs, and Steel Cleaning and Painting of Two Bridges.
|
| Location: |
|
| Resident Engineer: | Carmine LaVita![]() |
| Construction Contract Value: | $2,629,996.50 |
| Construction Bid Price: | $1,881,815.00 |
| Initial Construction Estimate: | $1,507,000.00 |
| District: | District 6 |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||