Project Description: |
RANDOLPH- BOSTON- BRAINTREE- STEEL SUPERSTRUCTURE CLEANING (FULL REMOVAL) AND PAINTING OF 3 BRIDGES: R-01-006 (344), B-16-261 (3FK) & B-21-027( 36E)
Randolph: Route 24 Northbound Curve G over Route 24 Southbound Curve S (Bridge No. R-01-006 (344)); Boston: Savin Hill Ave over I-93/US 1/Route 3 (Bridge No. B-16-261 (3FK)); and Braintree: Washington Street over Route 3 (Bridge No. B-21-027 (36E))
|
Location: |
|
Construction Begins: | Autumn 2017 |
Resident Engineer: | Thomas Mulry |
Construction Bid Price: | $1,042,680.00 |
District: | District 6 |
|
Bridges
|
|
|
|
|