Project Description: |
HINSDALE- RECONSTRUCTION OF ROUTE 143, FROM ROUTE 8 TO PERU T.L.
Project proposes to mill and overlay with minor widening to achieve bicycle accommodation. Project also includes drainage improvements, minor geometric improvements at two intersections; and sidewalk reconstruction.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Municipality |
Project Manager: | Joseph Gyujong Yoo |
Estimated Total Contract Cost: | $3,792,990.50 |
Estimated Total Federal Participating Construction Cost: | $4,200,000.00 |
District: | District 1 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|