Project Description:
WAKEFIELD- BRIDGE DECK REPLACEMENT, W-01-021 (2MF), HOPKINS STREET OVER I-95/ST 128
This bridge is structurally deficient and the work involves removing the old deck and replacing it with a new deck along with some structural steel repairs and substructure rrepairs to bring it out of the structurally deficient list.
Location:
  • Town of Wakefield
  • Construction Begins: Summer 2018
    Resident Engineer: Justin Charos
    Construction Bid Price: $1,738,033.00
    District: District 4

    Contracts (1) Progress
    # 102203 -- Construction Contract
    Bridge Deck Replacement and Related Work (Including Painting) Br. No. W-01-021 (Steel) Hopkins Street over I-95/Route 128. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/27/2018
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/25/2013
    Project Initiation Form PIF Entered 04/25/2013
    Project Initiation Form PRC Submitted 04/25/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 09/09/2017
    Project Management
    100% Design 100% Package Received 07/17/2017
    Final Design PS&E Received 08/22/2017
    Final Design PS&E to FAPRO 08/29/2017