DISTRICT 5- BRIDGE CLEANING AND RELATED WORK ALONG I-495 AND ROUTE 6, ROUTE 25 AND ROUTE 28 CORRIDORS
This project is to clean the bridges on the designated roadway corridors of accumulated road salt, pigeon debris, concrete and bituminous repair debris, sand, etc. in accordance with approved State bridge maintenance plan. Systematic Bridge Preservation activities, including deck joint replacement, deck repairs, wearing surface repairs, substructure repairs, and application of steel encapsulent coatings, shall also be performed.
Location:
Resident Engineer: Alex Lustikman
Construction Bid Price: $1,175,583.00
Initial Construction Estimate: $1,637,000.00
District: District 5

Contracts (1) Progress
# 90840 -- Construction Contract
Bridge Cleaning, Repairs and Related Work along Interstate 495 and Routes 6, 25 and 28 (Re-Advertised Project) 100% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/08/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/26/2013
    Project Initiation Form PIF Entered 04/26/2013
    Project Initiation Form PRC Submitted 04/26/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 01/17/2015
    Project Status Advertised 09/26/2015
    Project Management
    100% Design 100% Package Received 09/26/2014
    Final Design PS&E Received 01/13/2015
    Final Design PS&E Received 09/15/2015
    Final Design PS&E to FAPRO 01/13/2015
    Final Design PS&E to FAPRO 09/22/2015