Project Description:
SANDISFIELD- BRIDGE MAINTENANCE, S-03-033, ROUTE 8 (SOUTH MAIN STREET) OVER W. BRANCH FARMINGTON RIVER (PHASE II)
This contract is the second phase of systematic maintenance on this bridge (Project 607469 is Phase I). Proposed work includes partial stripping and painting of superstructure elements; to address faded and chalky areas, extensive peeling on the webs of exterior girders and minor areas at the girder ends and bearings.
Location:
  • Town of Sandisfield
  • Resident Engineer: Grant Haywood
    Construction Bid Price: $648,000.00
    District: District 1

    Contracts (1) Progress
    # 88112 -- Construction Contract
    Clean and Paint Br. No. S-03-033 (Including Steel Repairs) South Main Street (Route 8) over the West Branch Farmington River (Phase II). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/04/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/26/2013
    Project Initiation Form PIF Entered 04/26/2013
    Project Initiation Form PRC Submitted 04/26/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 05/16/2015
    Project Management
    100% Design 100% Package Received 03/27/2015
    Final Design PS&E Received 04/27/2015
    Final Design PS&E to FAPRO 05/12/2015