Project Description:
DALTON- BRIDGE MAINTENANCE, D-01-005, ROUTE 8 (MAIN STREET) OVER EAST BRANCH HOUSATONIC RIVER
This bridge is located approximately 0.13 miles east of North Street. Proposed work includes repairing the deck by full and partial depth excavation, applying epoxy bonding, repairing sidewalk scaling, repairing cracks in the backwalls by pressure injection, cleaning debris in the bridge seats, and flushing the scuppers. It is estimated that approximately 3% of the of the deck will require partial depth excavation, and another 20% may require full depth excavation. Proposed work also includes installation of new steel bars, in kind, where reinforcing steel exhibits section loss; and repair of spalling in the south end of the east backwall. Two-stage construction is anticipated; with traffic management to consist of alternating one-way traffic with a temporary solar signal.
Location:
  • Town of Dalton
  • Construction Begins: Summer 2016
    Resident Engineer: John Bedard
    Construction Bid Price: $688,508.00
    District: District 1

    Contracts (1) Progress
    # 93497 -- Construction Contract
    Bridge Deck, Joint and Railing Repairs Br. No. D-01-005 Route 8 (Main Street) over the East Branch of the Housatonic River. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/06/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/26/2013
    Project Initiation Form PIF Entered 04/26/2013
    Project Initiation Form PRC Submitted 04/26/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 03/05/2016
    Project Management
    100% Design 100% Package Received 11/27/2015
    Final Design PS&E Received 02/09/2016
    Final Design PS&E to FAPRO 02/24/2016