Project Description:
DISTRICT 5- BRIDGE MAINTENANCE AT VARIOUS LOCATIONS ALONG THE ROUTE 24 & ROUTE 3 CORRIDORS
This project is to perform maintenance cleaning of the bridges on the Rte. 24 and Rte. 3 corridors in accordance with the approved State bridge maintenance plan. This includes removal of salt residue, sand, concrete and bituminous repair debris, pigeon debris, etc.
Location:
Construction Begins: Summer 2017
Resident Engineer: Alex Lustikman
Construction Bid Price: $1,151,650.60
District: District 5

Contracts (1) Progress
# 98744 -- Construction Contract
Bridge Cleaning and Repairs at Various Locations along Routes 3 and 24 and Cleaning and Painting of Br. No. F-02-078 (Steel) Route 24 over Brayton Avenue. Completed

Bridges

Contract Dates
Notice to Proceed: 08/24/2017
Contract Information
Project Designer: In-House Boston
Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 04/26/2013
Project Initiation Form PIF Entered 04/26/2013
Project Initiation Form PRC Submitted 04/26/2013
Project Review Committee PRC Approved 05/17/2013
Project Status Advertised 11/05/2016
Project Management
100% Design 100% Package Received 06/20/2016
Final Design PS&E Received 07/18/2016
Final Design PS&E to FAPRO 10/21/2016