DISTRICT 4- SCHEDULED & EMERGENCY DRAINAGE REPAIR & IMPROVEMENTS AT VARIOUS LOCATIONS
District Four Wide drainage repair and improvements
Location:
Resident Engineer: Jose Rodriguez
Construction Bid Price: $847,813.00
Initial Construction Estimate: $690,000.00
District: District 4

Contracts (1) Progress
# 88044 -- Construction Contract
Scheduled and Emergency Drainage Repairs and Improvements at Various Locations (Re-advertised Project). Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/07/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/02/2013
    Project Initiation Form PIF Entered 05/02/2013
    Project Initiation Form PRC Submitted 05/02/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 09/27/2014
    Project Status Advertised 05/09/2015
    Project Management
    Final Design PS&E Received 09/17/2014
    Final Design PS&E Received 02/03/2015
    Final Design PS&E to FAPRO 09/24/2014
    Final Design PS&E to FAPRO 04/23/2015