BELCHERTOWN- WARREN- BRIDGE DEMOLITION OF B-05-023, WILSON STREET OVER NECRR, & W-07-012, OLD BOSTON POST ROAD OVER NAULTAUG BROOK
Existing single lane Timber Bridge Structure over the NECRR. Existing bridge is presently closed with a detour around the bridge.
Location:
  • Town of Belchertown
  • Town of Warren
  • Construction Begins: Winter 2016/2017
    Resident Engineer: David Virgilio
    Construction Bid Price: $522,599.66
    District: District 2

    Contracts (2) Progress
    # 77854 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 97768 -- Construction Contract
    Demolition of 2 Bridges Br. Nos. (B-05-023) Wilson Street over NECRR and (W-07-012) Old Boston Post Road over Naultaug Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/13/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2013
    Project Initiation Form PIF Entered 05/07/2013
    Project Initiation Form PRC Submitted 05/07/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 09/10/2016
    Project Management
    100% Design 100% Package Received 11/16/2015
    100% Design 100% Package Comments to DE 12/16/2015
    100% Design 100% Plans Approved 02/19/2016
    25% Design 25% Package Received 04/15/2015
    25% Design 25% Package Comments to DE 06/15/2015
    25% Design Design Public Hearing 09/03/2015
    75% Design 75% Package Received 11/16/2015
    75% Design 75% Package Comments to DE 12/16/2015
    75% Design 75% Plans Approved 02/19/2016
    Final Design PS&E Received 03/14/2016
    Final Design PS&E to Peer Reviewer 03/29/2016
    Final Design Peer Review Comments to DE 04/12/2016
    Final Design PS&E to FAPRO 09/02/2016
    Consultant Contract Process NTP Issued 11/19/2014