WEST SPRINGFIELD- BRIDGE RECONSTRUCTION, W-21-011, PROSPECT AVENUE OVER PVRR
Existing single span timber beam and deck superstructure supported on stone masonry abutments. Bridge is presently closed to traffic. Signs posted that disclose a "Dead End," at approaches.
Location:
  • Town of West Springfield
  • Design Responsibility: Consultant
    Project Manager: Lyris Liautaud
    Estimated Total Contract Cost: $581,350.00
    Estimated Total Federal Participating Construction Cost: $660,625.00
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2013
    Project Initiation Form PIF Entered 05/07/2013
    Project Initiation Form PRC Submitted 05/07/2013
    Project Review Committee PRC Approved 05/17/2013