Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ORANGE- BRIDGE REPLACEMENT, O-03-009, HOLTSHIRE ROAD OVER MILLERS RIVER
Existing 3-span steel beam with reinforced concrete deck superstructure. Superstructure sits on concrete piers and abutments. Concrete reveal and curbing with steel pipe railings on both sides of the bridge.
Location:
  • Town of Orange
  • Construction Begins: Spring 2018
    Resident Engineer: John Burek
    Construction Bid Price: $4,661,586.50
    District: District 2

    Contracts (2) Progress
    # 102136 -- Construction Contract
    Bridge Replacement Br. No. O-03-009 (Steel) Holtshire Road over Millers River. Completed
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/19/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2013
    Project Initiation Form PIF Entered 05/07/2013
    Project Initiation Form PRC Submitted 05/07/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 09/02/2017
    Project Management
    100% Design 100% Package Received 11/18/2016
    100% Design 100% Package Comments to DE 12/20/2016
    25% Design 25% Package Received 07/01/2015
    25% Design 25% Package Received 01/20/2016
    25% Design 25% Package Comments to DE 10/28/2015
    25% Design 25% Package Comments to DE 02/19/2016
    25% Design Design Public Hearing 04/07/2016
    75% Design 75% Package Received 07/01/2016
    75% Design 75% Package Comments to DE 08/31/2016
    Final Design PS&E Received 02/17/2017
    Final Design PS&E to Peer Reviewer 03/06/2017
    Final Design Peer Review Comments to DE 04/03/2017
    Final Design PS&E to FAPRO 08/21/2017