Project Description:
AMHERST- BRIDGE REPLACEMENT, A-08-008, MILL STREET OVER MILL RIVER
Existing single span steel beam with corrugated metal deck surface superstructure. Combined concrete and stone masonry abutments and wingwalls. Steel post bridge railing with timber rails.
Location:
  • Town of Amherst
  • Construction Begins: Spring 2018
    Resident Engineer: Joseph Burek
    Construction Bid Price: $2,161,066.00
    District: District 2

    Contracts (2) Progress
    # 101716 -- Construction Contract
    Bridge Replacement Br. No. A-08-008 (Precast Concrete Deck Beams) Mill Street over the Mill River. Completed
    # 77852 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/30/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2013
    Project Initiation Form PIF Entered 05/07/2013
    Project Initiation Form PRC Submitted 05/07/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 07/29/2017
    Project Management
    100% Design 100% Package Received 05/23/2017
    25% Design 25% Package Received 08/16/2016
    25% Design 25% Package Comments to DE 09/15/2016
    25% Design Design Public Hearing 11/15/2016
    75% Design 75% Package Received 01/31/2017
    Final Design PS&E Received 05/15/2017
    Final Design PS&E to FAPRO 07/13/2017