Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WINCHENDON- BRIDGE REPLACEMENT, W-39-015, NORTH ROYALSTON ROAD OVER TARBELL BROOK
Existing single span steel beam with corrugated metal deck superstructure. Superstructure rests on concrete abutments. Bridge railing consist of two W-beam sections attached to metal posts.
Location:
  • Town of Winchendon
  • Construction Begins: Autumn 2017
    Resident Engineer: Colby Roussel
    Construction Bid Price: $1,737,678.50
    District: District 2

    Contracts (2) Progress
    # 100204 -- Construction Contract
    Bridge Replacement Br. No. W-39-015 (NEXT Beams) North Royalston Road over Tarbell Brook Completed
    # 77848 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/29/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2013
    Project Initiation Form PIF Entered 05/07/2013
    Project Initiation Form PRC Submitted 05/07/2013
    Project Review Committee PRC Approved 05/17/2013
    Project Status Advertised 04/15/2017
    Project Management
    100% Design 100% Package Received 12/07/2016
    25% Design 25% Package Received 02/29/2016
    25% Design 25% Package Comments to DE 12/17/2015
    25% Design 25% Package Comments to DE 04/01/2016
    25% Design Design Public Hearing 05/26/2016
    75% Design 75% Package Received 09/09/2016
    75% Design 75% Package Comments to DE 11/02/2016
    75% Design 75% Plans Approved 11/18/2016
    Final Design PS&E Received 02/14/2017
    Final Design PS&E to Peer Reviewer 02/17/2017
    Final Design Peer Review Comments to DE 03/08/2017
    Final Design PS&E to FAPRO 03/27/2017