Project Description:
NORTON- CORRIDOR IMPROVEMENTS & RELATED WORK ON EAST MAIN STREET (ROUTE 123), FROM PINE STREET TO I-495
This project is proposed to address poor pavement condition, multi-modal, safety, drainage and related improvement needs, including geometric improvements at intersections. Work on this project includes mill/overlay, sidewalk construction traffic signal system installation at the Route 123/North/South Washington Street intersection and the I-495/Route 123 interchange. New sidewalks are proposed on the South side of Route 123 (East Main Street). Minor widening of the roadway is proposed to provide better bicycle accommodation. In addition, guardrail, curbing and drainage system upgrades are proposed.
Location:
  • Town of Norton
  • Construction Begins: Spring 2020
    Resident Engineer: Erik Trowbridge
    Construction Bid Price: $7,183,583.50
    District: District 5

    Contracts (1) Progress
    # 109101 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 123 (East Main Street) 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/21/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/08/2013
    Project Initiation Form PIF Entered 05/14/2013
    Project Initiation Form PRC Submitted 05/14/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 07/27/2019
    Project Management
    100% Design 100% Package Received 10/22/2018
    100% Design 100% Package Comments to DE 11/29/2018
    25% Design 25% Package Received 04/17/2015
    25% Design 25% Package Comments to DE 12/02/2015
    25% Design Design Public Hearing 07/18/2017
    75% Design 75% Package Received 10/31/2017
    75% Design 75% Package Comments to DE 02/09/2018
    Final Design PS&E Received 04/26/2019
    Final Design PS&E Received - Resub 1 06/13/2019
    Final Design PS&E Received - Resub 2 07/18/2019