Project Description:
WALTHAM- BRIDGE REPLACEMENT, W-04-006, WOERD AVENUE OVER CHARLES RIVER
Bridge Replacement with a modular pre-cast concrete system, with sidewalks on both sides and approach work
Location:
  • City of Waltham
  • Construction Begins: Spring 2019
    Resident Engineer: Gennady Shkolnikov
    Construction Bid Price: $2,725,737.20
    District: District 4

    Contracts (2) Progress
    # 105917 -- Construction Contract
    Bridge Replacement Br. No. W-04-006 (NEXT Beams) Woerd Avenue over the Charles River Completed
    # 77850 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/22/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/10/2013
    Project Initiation Form PIF Entered 07/23/2013
    Project Initiation Form PRC Submitted 11/14/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 09/15/2018
    Project Management
    25% Design 25% Package Received 10/19/2016
    25% Design 25% Package Comments to DE 12/19/2016
    25% Design Design Public Hearing 04/11/2017
    75% Design 75% Package Received 07/21/2017
    75% Design 75% Package Comments to DE 10/10/2017
    Final Design PS&E Received 01/03/2018
    Final Design PS&E Received - Resub 1 03/27/2018