Project Description:
TEWKSBURY- BRIDGE PRESERVATION, T-03-003, MILL STREET OVER SHAWSHEEN RIVER
Tewksbury bridge number T-03-003 carrying Mill Street over the Shawshen River will undergo scour repair and prevention measures. Minor improvements of guardrail and surface runoff control will also be performed.
Location:
  • Town of Tewksbury
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Justin Charos
    Construction Bid Price: $642,130.00
    District: District 4

    Contracts (2) Progress
    # 109300 -- Construction Contract
    Bridge Scour Repairs and Related Work Br. No. T-03-003 (Concrete) Mill Street over the Shawsheen River Completed
    # 60139 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support servives to support the Bridge Preservation/Betterment Program. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/10/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/10/2013
    Project Initiation Form PIF Entered 07/22/2013
    Project Initiation Form PRC Submitted 07/23/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 08/10/2019
    Project Management
    100% Design 100% Package Received 01/25/2019
    100% Design 100% Package Comments to DE 03/11/2019
    25% Design 25% Package Received 06/26/2018
    25% Design 25% Package Comments to DE 09/05/2018
    25% Design 25% Package Approved 09/20/2018
    25% Design Design Public Hearing 10/24/2018
    25% Design 25% Plans Complete 09/20/2018
    Final Design PS&E Received 05/13/2019
    Final Design PS&E to FAPRO 07/26/2019