Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
COLRAIN- INTERSECTION IMPROVEMENTS @ MAIN ROAD, JACKSONVILLE ROAD (ROUTE 112) & GREENFIELD ROAD
This project proposes to reconstruct this three-legged unsignalized intersection to improve traffic flow & sight distance, and improve pedestrian accommodation in the Colrain village center. Proposed work includes reconstructing the intersection and its approaches (approx. 0.1 mile north & south, and 0.5 mile west to the town offices) and creating an accessible network of sidewalks, ramps, and crosswalks to link popular village center locations. Project will include approx. 0.5 mile of new sidewalk, with landscaping and "streetscape” elements to promote pedestrian mobility in the village.
Location:
  • Town of Colrain
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Cathy Spaniol
    Construction Bid Price: $1,712,078.00
    District: District 1

    Contracts (1) Progress
    # 112694 -- Construction Contract
    Intersection Improvements and Related Work (Including Overhead Warning Signs) along a Section of Route 112 (Main/Jacksonville Roads) and Greenfield Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/28/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2013
    Project Initiation Form PIF Entered 07/17/2013
    Project Initiation Form PRC Submitted 07/18/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 08/29/2020
    Project Management
    100% Design 100% Package Received 05/01/2020
    100% Design 100% Package Comments to DE 06/08/2020
    25% Design 25% Package Received 02/19/2016
    25% Design 25% Package Comments to DE 03/15/2017
    25% Design 25% Package Received - Resub 1 11/10/2016
    25% Design Design Public Hearing 05/24/2018
    75% Design 75% Package Received 01/14/2019
    75% Design 75% Package Comments to DE 02/13/2019
    75% Design 75% Package Comments to DE 03/15/2019
    Final Design PS&E Received 07/30/2020
    Final Design PS&E Received - Resub 1 08/14/2020