Project Description:
SHELBURNE- INTERSECTION IMPROVEMENTS @ ROUTE 2 & COLRAIN/SHELBURNE ROAD
This project will make geometric improvements at the intersection of Route 2 and Colrain-Shelburne Road. The Route 2 West Safety Study (FRCOG 2009) and the 2010 HSIP Clusters Interactive Map (MassDOT) have both identified this intersection for potential safety improvements.
Location:
  • Town of Shelburne
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Michael Dostal
    Construction Bid Price: $729,981.96
    District: District 1

    Contracts (1) Progress
    # 97771 -- Construction Contract
    Intersection Improvements and Related Work Route 2 (Mohawk Trail) at Colrain Shelburne Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/17/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/17/2013
    Project Initiation Form PIF Entered 07/16/2013
    Project Initiation Form PRC Submitted 07/17/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 09/10/2016
    Project Management
    100% Design 100% Package Received 06/30/2016
    25% Design 25% Package Received 10/23/2015
    25% Design Design Public Hearing 02/23/2016
    75% Design 75% Package Received 10/23/2015
    75% Design 75% Package Comments to DE 11/06/2015
    Final Design PS&E Received 06/30/2016
    Final Design PS&E Received 08/12/2016
    Final Design PS&E to Peer Reviewer 08/12/2016
    Final Design Peer Review Comments to DE 08/16/2016
    Final Design PS&E to FAPRO 09/06/2016