Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
GEORGETOWN- NEWBURY- BORDER TO BOSTON TRAIL (NORTHERN GEORGETOWN TO BYFIELD SECTION)
The Northern Georgetown/Newbury section of the Border to Boston Trail is approximately 3.3 miles, extending from West Main Street (Route 97) in Georgetown to Bayfield in Newbury; 2.6 miles in Georgetown and 0.7 miles in Newbury will be comprised of an off-road shared use trail facility utilizing former railroad corridor and utility right of way.
Location:
  • Town of Georgetown
  • Town of Newbury
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $5,567,964.00
    Estimated Total Federal Participating Construction Cost: $6,069,642.82
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization.
    District: District 4
    Current Status: 25% Package Received - Resub 1 (as of 09/17/2019 )

    Contracts (1) Progress
    # 115750 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: GEORGETOWN
    NEWBURY
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $5,244,171.20
    State Cost: $1,311,042.80
    Total Cost: $6,555,214.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/22/2013
    Project Initiation Form PIF Entered 05/23/2013
    Project Initiation Form PRC Submitted 05/23/2013
    Project Review Committee PRC Approved 05/24/2013
    Project Management
    25% Design 25% Package Received 09/04/2012
    25% Design 25% Package Comments to DE 03/26/2013
    25% Design 25% Package Received - Resub 1 09/17/2019
    Consultant Contract Process NTP Issued 06/30/2018