Project Description: |
GEORGETOWN- NEWBURY- BORDER TO BOSTON TRAIL (NORTHERN GEORGETOWN TO BYFIELD SECTION)
The Northern Georgetown/Newbury section of the Border to Boston Trail is approximately 3.3 miles, extending from West Main Street (Route 97) in Georgetown to Bayfield in Newbury; 2.6 miles in Georgetown and 0.7 miles in Newbury will be comprised of an off-road shared use trail facility utilizing former railroad corridor and utility right of way.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Municipality |
Construction Begins: | Spring 2027 |
Project Manager: | Joseph Gyujong Yoo |
Estimated Total Contract Cost: | $5,567,964.00 |
Estimated Total Federal Participating Construction Cost: | $6,069,642.82 |
Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization. |
District: | District 4 |
Current Status: | 25% Package Received - Resub 1 (as of 09/17/2019 ) |
|
Bridges
|
|
|
|