Project Description:
BLANDFORD– RUSSELL- RESURFACING AND RELATED WORK ON I-90
Location:
  • Town of Blandford
  • Town of Russell
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Darin Aitken
    Construction Bid Price: $7,638,881.00
    District: District 1

    Contracts (1) Progress
    # 109464 -- Construction Contract
    Resurfacing and Related Work along a Section of Interstate 90 Westbound Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/07/2020
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/30/2013
    Project Initiation Form PIF Entered 05/30/2013
    Project Initiation Form PRC Submitted 05/30/2013
    Project Review Committee PRC Approved 06/03/2013
    Project Status Advertised 08/24/2019
    Project Management
    100% Design 100% Package Received 04/18/2019
    25% Design 25% Package Received 02/21/2019
    75% Design 75% Package Received 02/21/2019
    75% Design 75% Package Comments to DE 03/27/2019
    Final Design PS&E Received 04/18/2019
    Final Design PS&E Received - Resub 1 07/18/2019
    Final Design PS&E Received - Resub 2 08/13/2019