| Project Description: |
SHELBURNE- BRIDGE REPLACEMENT, S-11-006, BARDWELL FERRY ROAD OVER DRAGON BROOK
Full Bridge Replacement and Moderate approach work
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Municipality |
| Project Manager: | Tracy O Osimboni![]() |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 1 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||