Project Description:
LEE- LENOX- BRIDGE REPLACEMENT, L-05-020=L-07-003, VALLEY STREET OVER HOUSATONIC RIVER
Full Bridge Replacement and Moderate Approach work
Location:
  • Town of Lee
  • Town of Lenox
  • Construction Begins: Spring 2018
    Resident Engineer: Michael Cullett
    Construction Bid Price: $2,536,848.50
    District: District 1

    Contracts (4) Progress
    # 102138 -- Construction Contract
    Bridge Replacement Br. No. L-05-020=L-07-003 (Pre-Fabricated Steel Truss) Valley Street over the Housatonic River. Completed
    # 54619 -- Design -- Geotechnical
    Work will consist of laboratory and field testing, subsurface investigation inspection and design and analysis of complex foundation rehabilitation projects. Final
    # 58994 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 06/07/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/30/2013
    Project Initiation Form PIF Entered 05/31/2013
    Project Initiation Form PRC Submitted 05/31/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 09/02/2017
    Project Management
    100% Design 100% Package Received 02/07/2017
    25% Design 25% Package Received 04/13/2016
    25% Design 25% Package Comments to DE 07/05/2016
    25% Design 25% Package Received - Resub 1 08/31/2016
    25% Design Design Public Hearing 08/12/2016
    25% Design 25% Plans Complete 11/14/2016
    75% Design 75% Package Received 11/07/2016
    75% Design 75% Package Comments to DE 12/28/2016
    75% Design 75% Plans Approved 01/27/2017
    75% Design 75% Plans Complete 01/17/2017
    Final Design PS&E Received 02/07/2017
    Final Design PS&E to Peer Reviewer 04/18/2017
    Final Design Peer Review Comments to DE 04/28/2017
    Final Design PS&E to FAPRO 08/15/2017
    Final Design PS&E Received - Resub 1 04/12/2017
    Final Design PS&E Received - Resub 2 05/12/2017
    Final Design PS&E Received - Resub 3 02/21/2018
    Consultant Contract Process Scope to DE 03/31/2015
    Consultant Contract Process Workhours Approved 05/20/2015