AUBURN- BRIDGE REHABILITATION, A-17-046, I-90 INTERCHANGE 10 RAMP OVER ROUTE 12
This project will consist of the rehabilitation of the bridge that carries the I-90 Interchange 10 Ramp over Route 12 in Auburn. The work will consist of replacing the bridge superstructure and patching the substructure.
Location:
  • Town of Auburn
  • Construction Begins: Summer 2020
    Resident Engineer: Webster Larkin Sr
    Construction Bid Price: $7,684,172.76
    District: District 3

    Contracts (3) Progress
    # 111498 -- Construction Contract
    Bridge Superstructure Replacement and Related Work Br. No. A-17-046 (Steel) I-90 Interchange 10 over Route 12 (Southbridge Street) 70% Complete
    # 64322 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/02/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/04/2013
    Project Initiation Form PIF Entered 06/07/2013
    Project Initiation Form PRC Submitted 06/07/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 06/06/2020
    Project Management
    100% Design 100% Package Received 01/23/2020
    25% Design 25% Package Received 06/13/2018
    25% Design 25% Package Comments to DE 10/19/2018
    25% Design 25% Package Approved 06/14/2018
    25% Design Design Public Hearing 01/15/2019
    25% Design 25% Plans Complete 06/13/2018
    75% Design 75% Package Received 07/03/2019
    Final Design PS&E Received 04/27/2020
    Final Design PS&E Received - Resub 1 05/18/2020
    Consultant Contract Process NTP Issued 03/15/2017