Project Description:
NORWOOD- WESTWOOD- INTERSECTION IMPROVEMENTS AT UNIVERSITY AVENUE & CANTON STREET
Full depth intersection reconstruction including addition of turning lanes, drainage & signals improvements and raise the elevation of Canton St.
Location:
  • Town of Norwood
  • Town of Westwood
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Michael Furlong
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: 100% Package Received (as of 03/04/2014 )

    Contracts (1) Progress
    # 71613 -- Design -- Bridge Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for bridge, traffic and utility permit structural design and analysis assignments. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/11/2013
    Project Initiation Form PIF Entered 06/12/2013
    Project Initiation Form PRC Submitted 10/09/2013
    Project Management
    100% Design 100% Package Received 03/04/2014