Project Description:
SEEKONK- REHOBOTH- INTERSTATE MAINTENANCE & RELATED WORK ON I-195
The project consists of highway and bridge deck resurfacing, safety and environmental improvements between Mile Markers 0.0 and 4.3 in both directions for a total project length of 4.3 miles. The project also includes stormwater improvements along Route 114A.
Location:
  • Town of Rehoboth
  • Town of Seekonk
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Marc Cardinal
    Construction Bid Price: $8,879,265.60
    District: District 5

    Contracts (1) Progress
    # 105480 -- Construction Contract
    Resurfacing and Related Work (Including Br. No. R-04-018 and Ramps at Exit 1) along a Section of Interstate 195 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/28/2018
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/17/2013
    Project Initiation Form PIF Entered 06/17/2013
    Project Initiation Form PRC Submitted 06/17/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 08/11/2018
    Project Management
    100% Design 100% Package Received 03/27/2018
    100% Design 100% Package Comments to DE 04/30/2018
    25% Design 25% Package Received 10/06/2017
    25% Design 25% Package Comments to DE 12/06/2017
    75% Design 75% Package Received 10/06/2017
    75% Design 75% Package Comments to DE 12/06/2017
    Final Design PS&E Received 06/12/2018
    Final Design PS&E Received - Resub 1 07/17/2018