Project Description: |
MILLBURY- WORCESTER- RESURFACING & RELATED WORK ON ROUTE 146
The project consists of highway and bridge deck resurfacing, safety and environmental improvements between Mile Markers 16.5 and 20.6 in both directions for a total project length of 4.1 miles.
|
Location: |
|
Resident Engineer: | Stephen Shamoian![]() |
Construction Contract Value: | $6,124,219.50 |
Construction Bid Price: | $5,938,579.42 |
Initial Construction Estimate: | $5,617,000.00 |
District: | District 3 |
|