Project Description:
LEE- BIKEWAY CONSTRUCTION, FROM STOCKBRIDGE T.L. TO WEST PARK STREET (PHASE 1)
The Lee Bikeway would be a new bicycle facility (6.7 miles total length in Lee) consisting of both on-road and off-road sections from the Stockbridge town line to the Lenox town line. Off-road sections would consist of 10-ft wide pavement with 2-ft graded shoulders on each side. On-road sections would consist of paved shoulders (both directions) of appropriate width adjacent to the travel way. The current project concept is for three phases (from south to north): Phase 1 (607570) would consist of 3.18 miles on-road (Route 102) plus 0.93 miles off-road. Two sections of boardwalk are proposed (1000 feet total); one 60-ft bridge is proposed over an intermittent stream; and two sections of retaining wall are proposed (500 feet total). This phase of the bikeway would begin at the Lee/Stockbridge line and end at West Park Street in downtown Lee.
Location:
  • Town of Lee
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2028
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $5,532,636.15
    Estimated Total Federal Participating Construction Cost: $6,177,361.05
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: Design Public Hearing (as of 11/04/2021 )

    Contracts (1) Progress
    # 82513 -- Design -- Planning Studies
    Jacob's Ladder Trail Scenic Byway Lee Bikeway Project Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LEE
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $5,732,591.20
    State Cost: $1,433,147.80
    Total Cost: $7,165,739.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/19/2013
    Project Initiation Form PIF Entered 10/02/2013
    Project Initiation Form PRC Submitted 10/02/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Management
    25% Design 25% Package Received 02/22/2017
    25% Design 25% Package Comments to DE 05/02/2017
    25% Design 25% Package Rejected 05/02/2017
    25% Design 25% Package Received - Resub 1 04/11/2019
    25% Design Design Public Hearing 11/04/2021