Project Description:
LEE- BIKEWAY CONSTRUCTION, FROM ROUTE 102 TO WEST PARK STREET (PHASE 1)
The proposed project consists of an approximately 1-mile-long trail, providing accommodations for pedestrian and bicyclists through the town of Lee, and a segment of the Berkshire Bikeway. The shared use path will run along the east side of the Housatonic River, between the Lee Bank on West Park Street and the Big Y on Pleasant Street (Route 102). The shared use path will be an 8- to 10-foot-wide paved surface with a 2-foot-wide gravel shoulder on each side, which will transition to 12-foot-wide pile-supported boardwalks (8-foot travel way with 2-foot shoulders) at three locations where the path crosses brooks and/or wetlands. Improvements to the existing gravel parking lot on Route 102 (opposite Big Y Supermarket) and at the Route 102/Tyringham Road/Big Y entrance intersection to provide access to the parking lot are also proposed.
Location:
  • Town of Lee
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2029
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $5,532,636.15
    Estimated Total Federal Participating Construction Cost: $6,177,361.05
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: Design Public Hearing (as of 11/04/2021 )

    Contracts (1) Progress
    # 82513 -- Design -- Planning Studies
    Jacob's Ladder Trail Scenic Byway Lee Bikeway Project Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LEE
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

  • Scope to be from Route 102 to West Park Street (Phase 1)
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $5,732,591.20
    State Cost: $1,433,147.80
    Total Cost: $7,165,739.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/19/2013
    Project Initiation Form PIF Entered 10/02/2013
    Project Initiation Form PRC Submitted 10/02/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Management
    25% Design 25% Package Received 02/22/2017
    25% Design 25% Package Comments to DE 05/02/2017
    25% Design 25% Package Rejected 05/02/2017
    25% Design 25% Package Received - Resub 1 04/11/2019
    25% Design Design Public Hearing 11/04/2021
    Consultant Contract Process NTP Issued 01/29/2016