DENNIS- YARMOUTH- CONSTRUCTION OF A MULTI-USE PATH OVER THE BASS RIVER, INCLUDES NEW PEDESTRIAN BRIDGE D-07-007=Y-01-010
Work on this project consists of construction of a pedestrian bridge over the Bass River in the location of the former rail road bridge to provide a connection for the cape cod rail trail extension.
Location:
  • Town of Dennis
  • Town of Yarmouth
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Malcolm Lavalley
    Construction Bid Price: $3,497,962.80
    District: District 5

    Contracts (4) Progress
    # 54138 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 97593 -- Construction Contract
    Construction of the Cape Cod Rail Trail (CCRT) Extension Phase II Including Prefabricated Pedestrian Truss Br. No. D-07-007=Y-01-010 over the Bass River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/10/2017
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/20/2013
    Project Initiation Form PIF Entered 07/12/2013
    Project Initiation Form PRC Submitted 07/18/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 08/27/2016
    Project Management
    100% Design 100% Package Received 03/22/2016
    100% Design 100% Package Comments to DE 05/20/2016
    25% Design 25% Package Comments to DE 09/03/2014
    25% Design 25% Package Comments to DE 06/09/2015
    25% Design Design Public Hearing 05/20/2013
    75% Design 75% Package Received 03/28/2014
    75% Design 75% Package Comments to DE 12/18/2014
    Final Design PS&E Received 08/16/2016
    Final Design PS&E to Peer Reviewer 06/20/2016
    Final Design Peer Review Comments to DE 07/11/2016
    Final Design PS&E to FAPRO 08/22/2016