Project Description:
TAUNTON- CORRIDOR IMPROVEMENTS & RELATED WORK ON BROADWAY (ROUTE 138), FROM LEONARD STREET NORTHERLY TO PURCHASE STREET (PHASE 1)
This project is intended to address safety and multimodal accommodation along the corridor. Work in this project consists of pavement rehabilitation, sidewalk reconstruction, installation of bicycle lanes, and traffic signal upgrades at 3 intersections along Route 138: St. Mary's Square, E. Broadway and Purchase St. New pavement markings and signage are also proposed.
Location:
  • City of Taunton
  • Construction Begins: Summer 2020
    Resident Engineer: Emanuel Aguiar
    Construction Bid Price: $6,213,668.50
    District: District 5
    Current Status: Contractor has completed sidewalks, driveways, wheelchair ramps and pavement milling operations. Utility structure castings are being adjusted to finish grade. The surface course of HMA is scheduled to be placed on 5/24/23 with permanent pavement markings to follow. Anticipate narrow lanes and shoulder closures between 7:00 AM and 3:30 PM. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 05/16/2023)

    Contracts (1) Progress
    # 111307 -- Construction Contract
    Roadway Construction and Related Work (Including Signals) along a Section of Broadway (Route 138) 90% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/30/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/24/2013
    Project Initiation Form PIF Entered 06/26/2013
    Project Initiation Form PRC Submitted 06/26/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 05/09/2020
    Project Management
    100% Design 100% Package Received 06/17/2019
    100% Design 100% Package Comments to DE 07/29/2019
    100% Design 100% Plans Complete 07/26/2019
    25% Design 25% Package Received 05/12/2017
    25% Design 25% Package Comments to DE 10/16/2017
    25% Design Design Public Hearing 09/19/2018
    25% Design 25% Plans Complete 10/16/2017
    75% Design 75% Package Received 01/07/2019
    75% Design 75% Package Comments to DE 03/11/2019
    Final Design PS&E Received 10/04/2019
    Final Design PS&E to FAPRO 04/24/2020