DISTRICT 4- SCHEDULED & EMERGENCY BRIDGE DECK & JOINT REPAIRS AT VARIOUS LOCATIONS
This contract is always required to address emergency and routine deck and joint repairs. Though the current contract # 72756 (Projis # 6066070) has a contract completion date of July 2, 2014 but we have already spent approximately 70% of the funds. The new contract must be in place before we run out of funds in the existing contract, which at the current rate of spending are likely to last till September 2013. Either additional funds must be added to the existing contract or this new contract must be in place by that time.
Location:
Resident Engineer: Christopher Leahy
Construction Contract Value: $9,638,161.00
Construction Bid Price: $3,596,161.00
Initial Construction Estimate: $3,661,600.00
District: District 4

Contracts (1) Progress
# 82308 -- Construction Contract
Scheduled and Emergency Bridge Deck Repairs Including Joints at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/09/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/24/2013
    Project Initiation Form PIF Received 02/11/2014
    Project Initiation Form PIF Entered 06/24/2013
    Project Initiation Form PRC Submitted 06/24/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 05/10/2014
    Project Management
    100% Design 100% Package Received 11/14/2013
    Final Design PS&E Received 05/05/2014
    Final Design PS&E to FAPRO 05/06/2014