Project Description:
NORTHFIELD- BIKE/PED BRIDGE CONSTRUCTION TO REPLACE N-22-002, SCHELL BRIDGE OVER THE CONNECTICUT RIVER
Project will include the demolition of the existing deteriorated bridge structure and replacement with a new multi-span pedestrian bridge over the Connecticut River.
Location:
  • Town of Northfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2021/2022
    Project Manager: Anthony Christakis
    Estimated Total Contract Cost: $53,471,586.70
    Estimated Total Federal Participating Construction Cost: $56,036,756.55
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 09/11/2021 )

    Contracts (6) Progress
    # 54834 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 64326 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69765 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77891 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/08/2013
    Project Initiation Form PIF Entered 07/08/2013
    Project Initiation Form PRC Submitted 07/15/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Status Advertised 09/11/2021
    Project Management
    100% Design 100% Package Received 06/18/2021
    100% Design 100% Package Comments to DE 07/20/2021
    25% Design 25% Package Received 12/13/2019
    25% Design 25% Package Comments to DE 01/15/2020
    25% Design 25% Package Approved 09/17/2020
    25% Design Design Public Hearing 09/17/2020
    25% Design 25% Plans Complete 07/02/2020
    75% Design 75% Package Received 01/27/2021
    75% Design 75% Package Comments to DE 03/01/2021
    Final Design PS&E Received 08/20/2021
    Final Design PS&E to FAPRO 08/27/2021
    Final Design PS&E Received - Resub 1 04/28/2022