Project Description:
LEE- BRIDGE REPLACEMENT, L-05-004, MEADOW STREET OVER POWDER MILL BROOK
This project will provide a replacement bridge for the existing deteriorated steel stringer bridge. The replacement structure will most likely consist of a multi-beam steel stringer, or a pre-cast concrete butted box beam bridge with reinforced concrete deck, founded on pile-supported integral abutments located behind the existing abutments. Sheet pile scour protection will be placed in front of existing abutments, wing walls and retaining wall. Space between the sheet pile wall and front of footing will be filled with concrete, along with all scour voids below the footings.
Location:
  • Town of Lee
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2025/2026
    Project Manager: Joshua Bartus
    Estimated Total Contract Cost: $3,312,871.24
    Estimated Total Federal Participating Construction Cost: $3,643,894.67
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: 100% Package Received (as of 06/14/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LEE
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $2,810,522.40
    State Cost: $702,630.60
    Total Cost: $3,513,153.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/12/2013
    Project Initiation Form PIF Entered 07/12/2013
    Project Initiation Form PRC Submitted 07/18/2013
    Project Review Committee PRC Approved 07/25/2013
    Project Management
    100% Design 100% Package Received 06/14/2024
    25% Design 25% Package Received 01/15/2015
    25% Design 25% Package Comments to DE 01/26/2015
    25% Design 25% Package Received - Resub 1 08/12/2022
    25% Design Design Public Hearing 09/06/2023
    75% Design 75% Package Received 01/19/2024
    75% Design 75% Package Comments to DE 04/18/2024