Project Description:
WESTFIELD- SUPERSTRUCTURE REPLACEMENT, W-25-021, LOCKHOUSE ROAD OVER PVRR
The existing bridge consists of timber stringers and timber decking supported on stone masonry abutments. The proposed work consists of removing the existing timber superstructure, modifying the existing abutments by casting new cement concrete beamseat, and constructing a new structural steel superstructure with HMA wearing surface. Other incidental work consists of repairs to stone masonry abutments that are to remain, approach roadway work and guardrail upgrades.
Location:
  • City of Westfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Michael O'Dowd
    Estimated Total Contract Cost: $1,725,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/15/2013
    Project Initiation Form PIF Entered 09/04/2013
    Project Initiation Form PRC Submitted 09/04/2013
    Project Review Committee PRC Approved 09/16/2013
    Project Management