| Project Description: |
DISTRICT 4- SCHEDULED & EMERGENCY BRIDGE DECK & JOINT REPAIRS AT VARIOUS LOCATIONS
This contract is always required to address emergency and routine deck and joint repairs in the south area of District 4.
|
| Location: | |
| Resident Engineer: | Michael Gilardi![]() |
| Construction Contract Value: | $3,712,762.00 |
| Construction Bid Price: | $1,410,762.00 |
| Initial Construction Estimate: | $1,689,600.00 |
| District: | District 4 |
|