Project Description:
EVERETT- RECONSTRUCTION OF FERRY STREET, SOUTH FERRY STREET AND A PORTION OF ELM STREET
The project will reconstruct Ferry Street from the Malden city line (Belmont Street) to Route 16 and Elm Street between Ferry Street and Woodlawn Street. The work will include resurfacing, new sidewalks, wheelchair ramps and curb extensions. The traffic signals at five locations and the fire station will be upgraded. Signals at Chelsea Street will be replaced by a roundabout.
Location:
  • City of Everett
  • Construction Begins: Autumn 2021
    Resident Engineer: Dylan Boyle
    Construction Bid Price: $33,252,903.50
    District: District 4
    Current Status: Contractor continuing drainage work on Ferry Street between Broadway and Central Ave. Approximately two weeks of work remaining, once complete the contractor will shut down for the winter. (as of 01/15/2024)

    Contracts (3) Progress
    # 114626 -- Construction Contract
    Reconstruction and Related Work (Including Signals and Roundabout) on Ferry and South Ferry Streets and Sections of Chelsea and Elm Streets 78% Complete
    # 115797 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77889 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/13/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: Other types not listed
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor continuing drainage work on Ferry Street between Broadway and Central Ave. Approximately two weeks of work remaining, once complete the contractor will shut down for the winter.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/20/2013
    Project Initiation Form PIF Entered 08/27/2013
    Project Initiation Form PRC Submitted 10/15/2013
    Project Review Committee PRC Approved 04/07/2014
    Project Status Advertised 05/22/2021
    Project Management
    100% Design 100% Package Received 11/25/2020
    100% Design 100% Package Comments to DE 01/04/2021
    25% Design 25% Package Received 11/21/2016
    25% Design 25% Package Comments to DE 05/10/2017
    25% Design Design Public Hearing 08/02/2018
    75% Design 75% Package Received 03/17/2020
    75% Design 75% Package Comments to DE 07/02/2020
    Final Design PS&E Received 01/26/2021
    Final Design PS&E to Peer Reviewer 01/27/2021
    Final Design Peer Review Comments to DE 02/08/2021
    Final Design PS&E Received - Resub 1 04/22/2021