Project Description: |
BRAINTREE- WEYMOUTH- BRIDGE PRESERVATION TO 10 BRIDGES ALONG ROUTE 3
Work will consist of cleaning (full removal) and painting three (3) steel superstructures and substructure repairs and sealing to seven (10) bridges along the Route 3 corridor in Braintree and Weymouth.
|
Location: |
|
Resident Engineer: | Ryan Johnson |
Construction Contract Value: | $4,161,643.00 |
Construction Bid Price: | $2,699,690.00 |
Initial Construction Estimate: | $2,459,440.00 |
District: | District 6 |
|
Bridges
|
|
|
|
|