Project Description:
DISTRICT 3- TREE CLEARING AND TRIMMING AT VARIOUS LOCATIONS
The work to be done consists of selective clearing, removing and disposing of trees or remaining parts thereof located within the right of way of various state highways within the Mass DOT District 3 boundaries. The work will primarily be done to improve sight distance and provide clear path of travel along sidewalks.
Location:
Resident Engineer: Joel Babcock
Construction Contract Value: $1,919,809.65
Construction Bid Price: $1,719,809.65
Initial Construction Estimate: $1,799,880.00
District: District 3

Contracts (1) Progress
# 82665 -- Construction Contract
Scheduled and Emergency Tree Trimming and Removal and Sight Distance Clearing at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/02/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/30/2013
    Project Initiation Form PIF Entered 08/30/2013
    Project Initiation Form PRC Submitted 08/30/2013
    Project Review Committee PRC Approved 09/16/2013
    Project Status Advertised 05/31/2014
    Project Management
    Final Design PS&E Received 10/29/2013
    Final Design PS&E to FAPRO 01/22/2014