Project Description:
HEATH- BRIDGE REPLACEMENT, H-14-001, SR 8A (JACKSONVILLE STREET) OVER MILL BROOK
Work consists of replacing H-14-001.
Location:
  • Town of Heath
  • Construction Begins: Autumn 2017
    Resident Engineer: Cathy Spaniol
    Construction Bid Price: $976,898.60
    District: District 1

    Contracts (3) Progress
    # 101631 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide and bridge projects, for the purpose of maintaining Final
    # 58994 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 99545 -- Construction Contract
    Bridge Replacement Br. No. H-14-001 (Precast Arch) Jacksonville Stage Road (Route 8A) over Mill Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/27/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/05/2013
    Project Initiation Form PIF Entered 09/05/2013
    Project Initiation Form PRC Submitted 09/05/2013
    Project Review Committee PRC Approved 09/16/2013
    Project Status Approved 25% 12/15/2015
    Project Status Advertised 01/21/2017
    Project Management
    100% Design 100% Package Received 10/19/2016
    100% Design 100% Package Comments to DE 11/17/2016
    25% Design 25% Package Received 10/02/2015
    25% Design 25% Package Comments to DE 11/05/2015
    25% Design Design Public Hearing 02/09/2016
    75% Design 75% Package Received 07/22/2016
    Final Design PS&E Received 01/06/2017
    Final Design PS&E to Peer Reviewer 12/09/2016
    Final Design Peer Review Comments to DE 12/20/2016
    Final Design PS&E to FAPRO 01/09/2017
    Consultant Contract Process NTP Issued 03/20/2014