Project Description:
WARREN- BRIDGE REHABILITATION, W-07-002, MAIN STREET (SR 67) OVER QUABOAG RIVER
The proposed project is for the replacement of the bridge superstructure consisting of the concrete deck, sidewalks, railings and the steel beams that support the deck. Approximately 200 feet of roadway west of the bridge will be repaved and approximately 100 feet of roadway east of the bridge will be repaved. New sidewalks on each side of the roadway will be constructed from the bridge to connect to the recently constructed sidewalks along the roadway. The new bridge superstructure will be widened slightly to provide bicycle accommodations in each direction of travel consisting of a usable shoulder that will be in accordance with applicable design guides.
Location:
  • Town of Warren
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Richard Wonderlie
    Construction Bid Price: $3,337,978.00
    District: District 2

    Contracts (2) Progress
    # 109183 -- Construction Contract
    Bridge Replacement Br. No. W-07-002 (Steel) Route 67 (Main Street) over the Quaboag River Completed
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/28/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/05/2013
    Project Initiation Form PIF Entered 09/05/2013
    Project Initiation Form PRC Submitted 09/05/2013
    Project Review Committee PRC Approved 09/16/2013
    Project Status Advertised 08/03/2019
    Project Management
    100% Design 100% Package Received 04/30/2019
    100% Design 100% Package Comments to DE 05/31/2019
    100% Design 100% Plans Complete 06/14/2019
    25% Design 25% Package Received 08/21/2018
    25% Design 25% Package Comments to DE 09/21/2018
    25% Design Design Public Hearing 11/27/2018
    75% Design 75% Package Received 02/15/2019
    75% Design 75% Package Comments to DE 03/18/2019
    Final Design PS&E Received 07/01/2019
    Final Design PS&E to FAPRO 07/22/2019