Project Description:
BUCKLAND- CHARLEMONT- BRIDGE REHABILITATION, B-28-009=C-05-013, ST 2 OVER DEERFIELD RIVER
Work consists of rehabilitating B-28-009.
Location:
  • Town of Buckland
  • Town of Charlemont
  • Construction Begins: Autumn 2020
    Resident Engineer: Kevin Moriarty
    Construction Bid Price: $11,962,011.72
    District: District 1

    Contracts (3) Progress
    # 111658 -- Construction Contract
    Bridge Deck Replacement, Superstructure Repairs and Related Work (Including Painting) Br. No. B-28-009=C-05-013 (Steel) Route 2 (Mohawk Trail) over the Deerfield River Completed
    # 77854 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/24/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/05/2013
    Project Initiation Form PIF Entered 09/05/2013
    Project Initiation Form PRC Submitted 09/05/2013
    Project Review Committee PRC Approved 09/16/2013
    Project Status Advertised 06/20/2020
    Project Management
    100% Design 100% Package Received 02/25/2020
    100% Design 100% Package Comments to DE 04/03/2020
    25% Design 25% Package Received 02/01/2018
    25% Design 25% Package Received 09/09/2019
    25% Design 25% Package Comments to DE 04/12/2018
    25% Design 25% Package Received - Resub 1 01/18/2019
    75% Design 75% Package Received 09/09/2019
    Final Design PS&E Received 05/21/2020
    Final Design PS&E to FAPRO 06/09/2020