Project Description:
WILLIAMSBURG- BRIDGE REPLACEMENT, W-36-011 & W-36-017, BRIDGE STREET OVER THE MILL RIVER AND SOUTH MAIN STREET OVER THE MILL RIVER
The proposed project consists of replacing the Bridge Street and South Main Street bridges over the Mill River and rebuilding the portion of South Main Street between the two bridges. The traffic pattern in the area will be revised such that in the final condition, both bridges and the section of the South Main Street between the two bridges will create a one-way loop. Shared use accommodations will be added to the South Main Street bridge and extend through the reconstructed portion of South Main Street in accordance with applicable design guides.
Location:
  • Town of Williamsburg
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2028
    Project Manager: Alwin Ramirez
    Estimated Total Contract Cost: $9,877,486.30
    Estimated Total Federal Participating Construction Cost: $10,335,335.63
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 1
    Current Status: 25% Package Received - Resub 5 (as of 07/24/2024 )

    Contracts (1) Progress
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: WILLIAMSBURG
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $9,252,511.20
    State Cost: $2,313,127.80
    Total Cost: $11,565,639.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/05/2013
    Project Initiation Form PIF Entered 09/05/2013
    Project Initiation Form PRC Submitted 09/05/2013
    Project Review Committee PRC Approved 09/16/2013
    Project Management
    25% Design 25% Package Received 08/28/2020
    25% Design 25% Package Comments to DE 10/30/2020
    25% Design 25% Package Received - Resub 1 07/20/2021
    25% Design 25% Package Received - Resub 2 03/25/2022
    25% Design 25% Package Received - Resub 2 04/01/2022
    25% Design 25% Package Received - Resub 5 07/24/2024
    25% Design Design Public Hearing 07/27/2023