HEATH- BRIDGE REPLACEMENT, H-14-007, JACKSONVILLE STAGE ROAD (SR 8A) OVER THE WEST BRANCH BROOK
The intent of the proposed design is to replace the bridge to improve accessibility for all users. Presently, there are no existing shoulders on the bridge. The proposed improvements include lengthening of the bridge span and widening of the bridge width so that 3.0’ shoulders are provided for improved bicycle accommodation and accessibility. There are no sidewalks on the bridge nor off the bridge, both in the existing and proposed conditions.
Location:
  • Town of Heath
  • Construction Begins: Autumn 2024
    Resident Engineer: John Tietgens
    Construction Bid Price: $4,557,054.50
    District: District 1

    Contracts (2) Progress
    # 127857 -- Construction Contract
    Bridge Replacement, H-14-007, Jacksonville Stage Road (SR 8A) over the West Branch Brook 2% Complete
    # 77881 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/24/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/05/2013
    Project Initiation Form PIF Entered 09/05/2013
    Project Initiation Form PRC Submitted 09/05/2013
    Project Review Committee PRC Approved 09/16/2013
    Project Status Advertised 08/24/2024
    Project Management
    100% Design 100% Package Received 11/27/2023
    100% Design 100% Package Comments to DE 01/02/2024
    25% Design 25% Package Received 12/01/2022
    25% Design 25% Package Comments to DE 01/04/2023
    25% Design 25% Package Approved 03/31/2023
    25% Design 25% Package Approved 09/07/2023
    25% Design Design Public Hearing 05/02/2023
    25% Design 25% Plans Complete 03/31/2023
    75% Design 75% Package Received 08/07/2023
    75% Design 75% Package Comments to DE 09/07/2023
    Final Design PS&E Received 03/15/2024
    Final Design PS&E to FAPRO 08/09/2024
    Final Design PS&E Received - Resub 3 05/10/2024
    Consultant Contract Process Scope to DE 04/21/2022
    Consultant Contract Process NTP Issued 09/14/2022
    Consultant Contract Process Workhours Approved 07/22/2022