Project Description:
FITCHBURG- BRIDGE REHABILITATION, F-04-010, RIVER STREET (ST 31) OVER NORTH NASHUA RIVER
Work consists of rehabbing F-04-010.
Location:
  • City of Fitchburg
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Jeffrey Goyne
    Construction Bid Price: $6,339,017.00
    District: District 3

    Contracts (4) Progress
    # 115793 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 124171 -- Construction Contract
    Bridge Rehabilitation, F-04-010, River Street (ST 31) over North Nashua River
    # 69762 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77882 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/10/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/05/2013
    Project Initiation Form PIF Entered 09/05/2013
    Project Initiation Form PRC Submitted 09/05/2013
    Project Review Committee PRC Approved 09/16/2013
    Project Status Advertised 09/23/2023
    Project Management
    100% Design 100% Package Received 02/13/2023
    100% Design 100% Package Comments to DE 03/20/2023
    25% Design 25% Package Received 06/17/2020
    25% Design 25% Package Comments to DE 12/15/2020
    25% Design 25% Package Approved 10/21/2021
    25% Design 25% Package Received - Resub 1 10/30/2020
    25% Design 25% Package Received - Resub 2 06/16/2021
    25% Design 25% Package Received - Resub 3 06/29/2021
    25% Design Design Public Hearing 12/09/2021
    25% Design 25% Plans Complete 12/24/2020
    75% Design 75% Package Received 06/07/2022
    75% Design 75% Package Comments to DE 08/16/2022
    Final Design PS&E Received 06/09/2023
    Final Design PS&E Received - Resub 1 07/21/2023
    Final Design PS&E Received - Resub 2 08/14/2023