Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WEST SPRINGFIELD- BRIDGE PRESERVATION OF 7 BRIDGES ON I-90, FROM PIONEER VALLEY RAILROAD TO RIVERDALE ROAD (ROUTE 5)
Work under this project will consist of deck and joint repairs, substructure repairs, cleaning and painting and minor steel repairs.
Location:
  • Town of West Springfield
  • Construction Begins: Summer 2023
    Resident Engineer: Steven Zych
    Construction Bid Price: $5,264,474.60
    District: District 2

    Contracts (1) Progress
    # 122689 -- Construction Contract
    Bridge Preservation of 7 Bridges on I-90, From Pioneer Valley Railroad to Riverdale Road (Route 5) 16% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 09/12/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/09/2013
    Project Initiation Form PIF Entered 10/09/2013
    Project Initiation Form PRC Submitted 10/09/2013
    Project Review Committee PRC Approved 11/06/2013
    Project Status Advertised 07/01/2023
    Project Management
    100% Design 100% Package Received 04/10/2023
    100% Design 100% Package Comments to DE 05/09/2023
    Final Design PS&E Received 05/25/2023
    Final Design PS&E to FAPRO 06/25/2023