Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHICOPEE- LUDLOW- WILBRAHAM- RESURFACING & RELATED WORK ON I-90 (MM 50.0 - 59.0)
Work under this project will consist of resurfacing I-90 from MM 50.0 to MM 59.0. Also included will be drainage structure adjustments and curb/berm replacement and guardrail upgrades as required.
Location:
  • City of Chicopee
  • Town of Ludlow
  • Town of Wilbraham
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Hector Tineo
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • C13026 
    • C13053 
    • L16007 
    • L16009 
    • L16010 
    • L16014 
    • L16017 
    • L16022 
    • L16023 
    • L16024 
    See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project