CHICOPEE- LUDLOW- WILBRAHAM- RESURFACING & RELATED WORK ON I-90 (MM 50.0 - 59.0)
Work under this project will consist of resurfacing I-90 from MM 50.0 to MM 59.0. Also included will be drainage structure adjustments and curb/berm replacement and guardrail upgrades as required.
Location:
  • City of Chicopee
  • Town of Ludlow
  • Town of Wilbraham
  • Construction Begins: Summer 2023
    Resident Engineer: Jessica Gaudet
    Construction Bid Price: $38,691,846.25
    District: District 2

    Contracts (1) Progress
    # 121541 -- Construction Contract
    Resurfacing and Related Work along a Section of Interstate 90 52% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 07/20/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/08/2013
    Project Initiation Form PIF Entered 10/11/2013
    Project Initiation Form PRC Submitted 10/11/2013
    Project Review Committee PRC Approved 11/06/2013
    Project Status Advertised 03/04/2023
    Project Management
    100% Design 100% Package Received 01/30/2023
    75% Design 75% Package Received 05/13/2022
    75% Design 75% Package Comments to DE 06/29/2022
    Final Design PS&E Received 01/30/2023
    Final Design PS&E to FAPRO 02/28/2023