| Project Description: |
BEVERLY- MANCHESTER-BY-THE-SEA- RESURFACING & RELATED WORK ON ROUTE 127
Work consists of resurfacing and sidewalk reconstruction on Route 127.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Olivia Murphy![]() |
| Estimated Total Contract Cost: | $2,300,000.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 4 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges |
||||||
|
|
|
||||||||||||||||||||