Project Description:
METHUEN- RESURFACING & RELATED WORK ON ROUTE 28
Work consists of resurfacing and sidewalk reconstruction on Route 28 from the Route 213 interchange to the New Hampshire state line.
Location:
  • Town of Methuen
  • Resident Engineer: Erik Berzins
    Construction Contract Value: $803,409.22
    Construction Bid Price: $671,451.50
    Initial Construction Estimate: $600,000.00
    District: District 4

    Contracts (3) Progress
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86123 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 28 (Broadway Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/14/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/23/2013
    Project Initiation Form PIF Entered 09/23/2013
    Project Initiation Form PRC Submitted 09/23/2013
    Project Review Committee PRC Approved 10/01/2013
    Project Status Advertised 12/20/2014
    Project Management
    100% Design 100% Package Received 11/14/2014
    25% Design 25% Package Received 09/16/2014
    75% Design 75% Package Received 09/16/2014
    75% Design 75% Package Comments to DE 10/15/2014
    75% Design 75% Package Comments to DE 10/17/2014
    Final Design PS&E Received 11/14/2014
    Final Design PS&E Received 07/09/2015
    Final Design PS&E to FAPRO 12/16/2014